In the late nineteen eighties, electric utility companies, such as Kansas City Power and Light (KCPL), recognized the viability of extending the life of power plants by repairing or replacing major components instead of building entirely new facilities. As part of a strong life management program, a life evaluation can postpone the replacement of major components to future years. A physical condition assessment is the first step in a life evaluation. It requires the following information: 1) original design data; 2) component operating data; 3) knowledge of current industry practices; and 4) detailed component inspections. The second step in a life evaluation is an economic life assessment to ascertain the component’s current loss of performance. The cost associated with operating the component in its current degraded state is then compared to the cost of repairing or replacing the component. Based on this cost comparison, a course of action is determined to optimize the component’s life cycle cost. This paper describes the methodology of life management and its application to a feedwater heater at Kansas City Power and Light.

1.
Beckerdite, G., 1991, “Life Assessment and Management Program for Feedwater Heaters,” KCPL LAMP, Kansas City Power and Light Company, Kansas City, MO.
2.
Bell, R., 1995, “Condition Assessment of Closed Feedwater Heater,” EPRI FW Heater Technology Symposium, Electric Power Research Institute, Palo Alto, CA, September 22–24.
3.
Bell, R. J., Conley, E. F., and Deleon, A. M., 1994, “Life Extension Analysis of Condensers and Feedwater Heaters,” HES Seminar, Heat Exchanger Systems, Inc., Boston, MA.
4.
Bell, R. J., Conley, E. F., and Diaz-Tous, I., 1991, “Manual for Investigation and Correction of Feedwater Heater Failures,” Electric Power Research Institute, Project No. GS-7390, Sept.
5.
Bell, R., and Diaz-Tous, I., 1984, “High Reliability Feedwater Heaters,” Edison Electric Institute Prime Movers and Nuclear Committee, Edison Electric Institute, New Orleans, LA, January 29.
6.
Jacobstein, A. R., Quinn, J. A., Wadsworth, F. L., and Wellens, R. S., 1981, Failure Cause Analysis Feedwater Heaters, Electric Power Research Institute, Technical Report No. CS-1776, Apr.
7.
Krzywosz, K., 1995, “Feedwater Heater Condition Assessment—an NDE Perspective,” EPRI FW Heater Technology Symposium, Electric Power Research Institute, Palo Alto, CA, September 22–24.
8.
Ranganathan, K., Singh, G. P., and Tsou, J., 1995, “Feedwater Heater Performance Evaluation Using the HEW Workstation,” EPRI FW Heater Technology Symposium, Electric Power Research Institute, Palo Alto, CA, September 22–24.
9.
Tsou, J. L., 1990, “Calculation Procedure,” EPRI Heat Rate Improvement Conference, Electric Power Research Institute, Project No. GS-6985, Sept.
10.
Yokell, S., 1995, “Guide to Plugging Feedwater Heaters,” EPRI FW Heater Technology Symposium, Electric Power Research Institute, Palo Alto, CA, September 22–24.