A shutdown operation of a large size steam turbine could possibly cause flashing phenomena of the pooled drain water in low-pressure heaters. The boiled steam is sometimes in the same amount as the main flow in the case where shutdown is executed during low load conditions, and returns to the steam flow path through the extraction lines. A series of experimental work with a subscale model turbine facility has been carried out to investigate the vibration stress behavior, and the steady and unsteady pressures under the flashing back (FB) conditions. It was observed that the blades of the two stages before the last stage (L-2) and a stage before the last stage (L-1) presented their peak vibration stresses immediately after the flash-back flow reached the turbine. In the meantime, the vibration stresses of the last stage (L-0) blades were reduced for a few tens of seconds. It can be thought that the flash-back flow pushed out the reverse flow region around the L-0 blades and allow the blades to be more stable. A detailed examination with measured data of the L-2 blade explained that, as long as the flash-back flow has small wetness, the blade is excited in its specific vibration modes in larger than eighth harmonic of rotational speed, but once the flash-back flow carries water droplets, the fluid force in random frequencies remarkably increases and excites the blade in less than seventh harmonic range.

References

1.
Ikeuchi
,
K.
,
Kashiwabara
,
K.
,
Hisano
,
K.
,
Namura
,
K.
, and
Uenishi
,
A.
,
1982
, “
Recent Technology of Long Blade for Steam Turbine
,”
Therm. Nucl. Power
,
33
(
5
), pp.
47
57
(in Japanese).
2.
Iwanaga
,
K.
,
Kawakami
,
H.
,
Hisa
,
S.
, and
Ogata
,
H.
,
1985
, “
Reliability of Last Stage Blade for Steam Turbine Under Minimum Load Operation
,”
Therm. Nucl. Power
,
36
(
9
), pp.
21
34
(in Japanese).
3.
Saito
,
E.
,
Yamashita
,
Y.
, and
Kudo
,
T.
,
2009
, “
Basic Study of Random Vibration for Turbine Blade Structure
,”
International Conference on Power Engineering (ICOPE-09)
, Kobe, Japan, Nov. 16–19, pp.
2-511
2-516
.
4.
Nakamura
,
T.
,
Isobe
,
N.
,
Segawa
,
K.
, and
Saito
,
T.
,
2009
, “
Highly-Reliable Design Technology of Steam Turbine for Nuclear Power Plant
,”
Hitachi Hyoron
,
91
(
2
), pp.
224
225
(in Japanese).
5.
Segawa
,
K.
,
2010
, “
Flow Measurement Technologies Steam Turbines
,”
Turbomachinery
,
38
(
9
), pp.
20
27
(in Japanese).
6.
Truckenmüller
,
F.
,
Gerschütz
,
W.
,
Stetter
,
H.
, and
Hosenfeld
,
H.-G.
,
1999
, “
Examination of the Dynamic Stress in the Moving Blades of the Last Stage in a Low-Pressure Model Turbine During Windage
,” 3rd European Conference on Turbomachinery: Fluid Dynamics and Thermodynamics, London, Mar. 2–5, Paper No. C557/124, pp.
757
770
.
7.
Gerschütz
,
W.
,
Casey
,
M.
, and
Truckenmüller
,
F.
,
2005
, “
Experimental Investigations of Rotating Instabilities in the Last Stage of a Low Pressure Model Steam Turbine During Windage
,”
J. Power Energy
,
219
(
A6
), pp.
499
510
.10.1243/095765005X31379
8.
Sigg
,
R.
,
Heinz
,
C.
, and
Casey
,
M. V.
,
2009
, “
Numerical and Experimental Investigation of a Low Pressure Steam Turbine During Windage
,”
Proc. Inst. Mech. Eng., Part A
,
223
(
6
), pp.
697
708
.10.1243/09576509JPE826
9.
Shibukawa
,
N.
,
Tejima
,
T.
,
Iwasaki
,
Y.
,
Murakami
,
I.
, and
Saito
,
I.
,
2011
, “
A Correlation Between Vibration Stresses and Flow Features of Steam Turbine Long Blades in Low Load Conditions
,”
ASME
Paper No. GT2011-46368.10.1115/GT2011-46368
You do not currently have access to this content.