Skip to Main Content
Skip Nav Destination
Consensus for the Lay-up of Boilers, Turbines, Turbine Condensors, and Auxiliary Equipment (CRTD-66)Available to Purchase
By
The Turbine/Turbine Condenser Lay-up Task Group and the Boiler Lay-up Task group for the Water Technology Subcommittee of the ASME Research and Technology Committee on Water and Steam in Thermal Power Systems
The Turbine/Turbine Condenser Lay-up Task Group and the Boiler Lay-up Task group for the Water Technology Subcommittee of the ASME Research and Technology Committee on Water and Steam in Thermal Power Systems
Search for other works by this author on:
ISBN:
9780791836187
No. of Pages:
68
Publisher:
ASME Press
Publication date:
2002

The following is a list of items which generally need to be addressed when preparing to lay-up a unit or system;

  1. Safety — of personnel and property

  2. Systems and/or equipment to lay-up

  3. Condition of unit(s)

  4. Estimated period of lay-up and work to be performed

  5. The lay-up environment such as possibility of freezing

  6. Estimated time available to start up unit

  7. Availability of manpower to inspect and monitor unit(s) during lay-up

  8. Value of unit and possible financial consequences of lay-up procedure selected

  9. Compatibility between lay-up and operational chemical treatments

  10. Disposal of lay-up solutions

  11. System auxiliaries such as fuel additive feed systems, soot blowers etc.