It is common in a refinery that some piping systems have to handle several flow conditions. However, when a new proposed condition implies the filling of an existing 68″ (1727 mm) line with molten Sulfur, which was initially designed for gas operation, a well thought engineering case study is required to guarantee that no damage will occur under the new operating conditions.

This paper covers the procedures employed to qualify the integrity of a 68″ (1727 mm) piping system, initially designed to carry Sulfur vapors and required to handle occasional filling with molten Sulfur due to operational demands.

The procedures of reviewing the initial configuration, design of modifications and reinforcements to the piping system and the use of Finite Element Analysis (FEA) in order to qualify several unique support configurations are explained in this paper.