The targeted 24.5 months of commissioning time for the ongoing SKN unit #1 project in Korea is a tough challenge in view of saving at least 7 months from the previous 32 months for UCN unit #3 project that has been a prior version of OPR1000 and also the reference plant of this unit. Such commissioning time-saving has been made possible by introducing renovated technology, optimization of commissioning technique, and adoption of lessons-learned from the previous projects. Our experiences are discussed herein with respect to the scheduling of commissioning operation of previous NPP projects on a milestone basis, including trouble areas that could cause schedule delay and our approaches adopted for solving the key issues. In addition, this paper will introduce a summarized 24 month commissioning schedule which has been optimized to the most efficient level by reflecting the prior project experience, and applying the new techniques and methods.
Skip Nav Destination
Close
Sign In or Register for Account
ASME 2010 Pressure Vessels and Piping Division/K-PVP Conference
July 18–22, 2010
Bellevue, Washington, USA
Conference Sponsors:
- Pressure Vessels and Piping Division
ISBN:
978-0-7918-4928-6
PROCEEDINGS PAPER
The Application of Optimized Commissioning Schedule
Yong Ro Lee
Yong Ro Lee
Korea Power Engineering Company, Inc., Yongin, Gyeonggi, Korea
Search for other works by this author on:
Yong Ro Lee
Korea Power Engineering Company, Inc., Yongin, Gyeonggi, Korea
Paper No:
PVP2010-25560, pp. 199-204; 6 pages
Published Online:
January 10, 2011
Citation
Lee, YR. "The Application of Optimized Commissioning Schedule." Proceedings of the ASME 2010 Pressure Vessels and Piping Division/K-PVP Conference. ASME 2010 Pressure Vessels and Piping Conference: Volume 9. Bellevue, Washington, USA. July 18–22, 2010. pp. 199-204. ASME. https://doi.org/10.1115/PVP2010-25560
Download citation file:
- Ris (Zotero)
- Reference Manager
- EasyBib
- Bookends
- Mendeley
- Papers
- EndNote
- RefWorks
- BibTex
- ProCite
- Medlars
Close
Sign In
6
Views
0
Citations
Related Proceedings Papers
Related Articles
Supervisory Control of Dynamical Systems With Uncertain Time Delays
J. Vib. Acoust (December,2010)
Weld Material Investigations of a WWER-440 Reactor Pressure Vessel: Results From the First Trepan Taken From the Former Greifswald NPP
J. Eng. Gas Turbines Power (March,2009)
Japanese Activities Concerning Nuclear Codes and Standards—Part I
J. Pressure Vessel Technol (February,2006)
Related Chapters
Constraints
Nonlinear Regression Modeling for Engineering Applications: Modeling, Model Validation, and Enabling Design of Experiments
Introduction
Consensus on Pre-Commissioning Stages for Cogeneration and Combined Cycle Power Plants
Qualitative Analysis for Predator-Prey Systems with Time Delays and Simplified Holling Type-IV Functional Response
International Conference on Computer Technology and Development, 3rd (ICCTD 2011)