Offshore pipelines may face many threats. Apart from internal and external corrosion third party threats represent major hazards to submarine pipelines. Recent pipeline leaks caused by third party as well as construction and installation have been repaired online in a two-step process involving installation of a leak clamp followed by a permanent repair by installation of a welded stand-off sleeve. The welding has depending on the water depth been executed in a hyperbaric habitat or in shallow water using purpose built cofferdams. A concept proposed by DNV GL has been successfully applied to repair of leaking submarine pipelines. To ensure the safety of the repair crew the concepts involves using a gas containment barrier installed over a traditional mechanical leak clamp. The gas containment barrier is either purged with inert gas or nitrogen or it is maintained with a constant inert gas pressure that is monitored continuously during the repair. In the event of a sudden gas leak into the gas containment barrier a pre-set pressure relief valve will open and dump the gas leak outside the habitat. This paper describes the details of a few cases of leaking submarine gas pipelines and the immediate causes of the leak, the repair method selection, the repair method details, cofferdam or hyperbaric welding qualification and execution. The paper also describes the various steps in the process to ensure that the pipeline damage is stable and that the repairs can be safely undertaken to restore the pipelines to their original design condition without reduction of pressure or flow rate. The paper describes the method of global and local finite element analyses as well as fracture mechanics assessment by FEA to assess the stability of the flaws causing the gas leaks. The pipelines in question have all been gas transmission lines carrying gas to gas fired power plants for which gas pressure reduction or shutdown were completely unacceptable. Future development is expected to involve development of remotely controlled repairs using similar concepts at water depths where diver/welders cannot be employed due to the various country regulations or simply because the water depths are too deep for saturation divers. Methodology according to DNV RP-A203 [1] is described for qualification of new technology for underwater pipeline repairs. Further references are made to the recent updates to the DNV RP-F113 Pipeline Subsea Repair [2] with regards to requirements for “live” pipeline repairs. The DNV RP-F113 refers to the PRCI Weld Thermal analyses [3] and requirements to perform full scale mock-up tests of the repair as part of the repair method qualification based on DNV OS-F101 Submarine Pipelines [4].
Skip Nav Destination
ASME 2016 35th International Conference on Ocean, Offshore and Arctic Engineering
June 19–24, 2016
Busan, South Korea
Conference Sponsors:
- Ocean, Offshore and Arctic Engineering Division
ISBN:
978-0-7918-4995-8
PROCEEDINGS PAPER
Cofferdam and Hyperbaric “Live” Repair of Gas Pipeline Leaks
Jens P. Tronskar,
Jens P. Tronskar
DNV GL Oil and Gas Technology Centre, Singapore, Singapore
Search for other works by this author on:
Chon Gee Lee
Chon Gee Lee
DNV GL Oil and Gas Technology Centre, Singapore, Singapore
Search for other works by this author on:
Jens P. Tronskar
DNV GL Oil and Gas Technology Centre, Singapore, Singapore
Chon Gee Lee
DNV GL Oil and Gas Technology Centre, Singapore, Singapore
Paper No:
OMAE2016-55077, V004T03A004; 11 pages
Published Online:
October 18, 2016
Citation
Tronskar, JP, & Lee, CG. "Cofferdam and Hyperbaric “Live” Repair of Gas Pipeline Leaks." Proceedings of the ASME 2016 35th International Conference on Ocean, Offshore and Arctic Engineering. Volume 4: Materials Technology. Busan, South Korea. June 19–24, 2016. V004T03A004. ASME. https://doi.org/10.1115/OMAE2016-55077
Download citation file:
25
Views
Related Proceedings Papers
Related Articles
Profiles of Two JOMAE Associate Editors (A Continuing Series)
J. Offshore Mech. Arct. Eng (October,2021)
Rupture Hardware Minimization in Pressurized Water Reactor
Piping
J. Pressure Vessel Technol (February,1989)
Fukushima Unit 2 Accident Simulation With MELCOR 2.1
ASME J of Nuclear Rad Sci (April,2018)
Related Chapters
Iwe and Iwl
Companion Guide to the ASME Boiler and Pressure Vessel Code, Volume 2, Third Edition
IWE and IWL
Companion Guide to the ASME Boiler & Pressure Vessel Code, Volume 2, Second Edition: Criteria and Commentary on Select Aspects of the Boiler & Pressure Vessel and Piping Codes
Iwe and Iwl
Companion Guide to the ASME Boiler and Pressure Vessel Code, Volume 2, Fourth Edition