There have been several recent weld failures either during the initial post construction hydrostatic tests, or immediately following construction. Girth welds typically do not fail as a result of internal hoop loads without the contribution of loads due to out side forces. External loading should be considered during design, welding procedure development, construction, and pipeline operations. This paper presents one example where a girth weld failed as a result of preexisting 1940’s weld imperfections and recent, 1980’s, external loading. This analysis of the girth weld failure in the 30-inch pipeline included an initial failure analysis, a fracture mechanics analysis, and a finite element analysis that integrated the pipe-soil interaction, as well as localized stresses associated with weld imperfections. A critical part of this study was to evaluate how changes in soil conditions associated with a drought followed by soil saturation associated with rainfall, contributed to lack of local support and increased overburden loads associated with the saturated soil. The failure analysis of the ruptured girth weld and surrounding pipe concluded that the failure of the girth weld was caused by increased bending loads imposed on the pipeline after recent construction activities, and that the fracture initiated at a lack-of-penetration/fusion imperfection that was 20 1/4-inches long and 0.110 inches deep. A coupled investigation using finite element and fracture mechanics analyses verified numerically that with reduced-strength soil, stresses were generated in the girth weld of sufficient magnitude to cause a fracture. Temperature, terrain, and fatigue were considered, but were not deemed to significant enough to affect the stresses or other conditions that resulted in the failure. The overriding observation of this study is that no single factor contributed to the failure that occurred. Rather, the girth weld failure was the result of weld imperfections that generated elevated stresses due to excessive loads imparted to the pipe due to settlement associated with non-compact backfill associated with excavation work. Had the pipe not displaced vertically due to localized soil conditions, it is unlikely that the pipeline would have failed. The recent excavation activities were adequate for normal soil conditions; however, dry soil at the time of construction resulted in lack of compaction and excessive moisture just prior to the failure that generated in differential settlement and heavy overburden, combined with lack of penetration imperfection in the girth weld in question, resulted in generating excessive bending stresses that contributed to the eventual failure of the pipeline.
Skip Nav Destination
2010 8th International Pipeline Conference
September 27–October 1, 2010
Calgary, Alberta, Canada
Conference Sponsors:
- International Petroleum Technology Institute and the Pipeline Division
ISBN:
978-0-7918-4420-5
PROCEEDINGS PAPER
Girth Weld Failure in a Large Diameter Gas Transmission Pipeline
Ron Scrivner,
Ron Scrivner
Stress Engineering Services, Inc., Houston, TX
Search for other works by this author on:
Butch Exley,
Butch Exley
Williams Gas Pipeline, Houston, TX
Search for other works by this author on:
Chris Alexander
Chris Alexander
Stress Engineering Services, Inc., Houston, TX
Search for other works by this author on:
Ron Scrivner
Stress Engineering Services, Inc., Houston, TX
Butch Exley
Williams Gas Pipeline, Houston, TX
Chris Alexander
Stress Engineering Services, Inc., Houston, TX
Paper No:
IPC2010-31525, pp. 791-809; 19 pages
Published Online:
April 4, 2011
Citation
Scrivner, R, Exley, B, & Alexander, C. "Girth Weld Failure in a Large Diameter Gas Transmission Pipeline." Proceedings of the 2010 8th International Pipeline Conference. 2010 8th International Pipeline Conference, Volume 1. Calgary, Alberta, Canada. September 27–October 1, 2010. pp. 791-809. ASME. https://doi.org/10.1115/IPC2010-31525
Download citation file:
12
Views
Related Proceedings Papers
Related Articles
Failure Analysis of Rapid Prototyped Tooling in Sheet Metal Forming—V-Die Bending
J. Manuf. Sci. Eng (February,2005)
Cover Requirement and Stability of Horizontally Bent Buried Pipelines
J. Pressure Vessel Technol (April,2012)
Prestressing Buried Pipelines by Heating With Air
J. Offshore Mech. Arct. Eng (November,1993)
Related Chapters
HIGH STRAIN WELD SOLUTIONS FOR GEOHAZARD ACTIVE ENVIRONMENT
Pipeline Integrity Management Under Geohazard Conditions (PIMG)
Better Risk Management for Underground Pipelines and Tunnels Using Sound Geotechnical Interpretation
Geological Engineering: Proceedings of the 1 st International Conference (ICGE 2007)
Subsection NB—Class 1 Components
Companion Guide to the ASME Boiler & Pressure Vessel Code, Volume 1, Second Edition