An industrial gas turbine has the characteristic that turbine output decreases on hot summer days when electricity demand peaks. For GE-F5 gas turbines of Mashad Power Plant when ambient temperature increases 1° C, compressor outlet temperature increases 1.13° C and turbine exhaust temperature increases 2.5° C. Also air mass flow rate decreases about 0.6 kg/sec when ambient temperature increases 1° C, so it is revealed that variations are more due to decreasing in the efficiency of compressor and less due to reduction in mass flow rate of air as ambient temperature increases in constant power output. The cycle efficiency of these GE-F5 gas turbines reduces 3 percent with increasing 50° C of ambient temperature, also the fuel consumption increases as ambient temperature increases for constant turbine work. These are also because of reducing in the compressor efficiency in high temperature ambient. Steam injection in gas turbines is a way to prevent a loss in performance of gas turbines caused by high ambient temperature and has been used for many years. VODOLEY system is a steam injection system, which is known as a self-sufficient one in steam production. The amount of water vapor in combustion products will become regenerated in a contact condenser and after passing through a heat recovery boiler is injected in the transition piece after combustion chamber. In this paper the influence of steam injection in Mashad Power Plant GE-F5 gas turbine parameters, applying VODOLEY system, is being observed. Results show that in this turbine, the turbine inlet temperature (T3) decreases in a range of 5 percent to 11 percent depending on ambient temperature, so the operating parameters in a gas turbine cycle equipped with VODOLEY system in 40° C of ambient temperature is the same as simple gas turbine cycle in 10° C of ambient temperature. Results show that the thermal efficiency increases up to 10 percent, but Back-Work ratio increases in a range of 15 percent to 30 percent. Also results show that although VODOLEY system has water treatment cost but by using this system the running cost will reduce up to 27 percent.

1.
Horlock J H, 1992, “Combined Power Plants Including Combined Cycle Gas Turbine (CCGT plants,” First Edition, Chapter 7 Page 256, printed in U.K, by B.P.C.C.
2.
Carlos Hartel, Peter Pfeiffer, 2003, “Model Analysis of High-Fogging Effects on the Work of Compression,” Proceeding of ASME Turbo Expo, Power For Land, Sea and Air, Atlanta, Georgia, USA.
3.
Zheng Q., Li M. and Sun Y., 2003, “Thermodynamic Performance of Wet Compression and Regenerative (WCR) Gas Turbine,” Harbin Engineering University, Harbin 150001 China, Proceeding of ASME Turbo Expo, Power for Land, Sea, and Air, Atlanta, Georgia.
4.
Mohanty and G.Paloso JR, 1993, “Enhancing Gas Turbine Performance By Intake Air Cooling Using an Absorption Chiller,” School of Environment, Resources and Development, Asian Institute of Technology, P.O.Box 2754, Bangkok 10501, Thailand.
5.
Lumpugnano V., 2000, “Various Turbine Inlet Air Cooling Mechanical Refrigerant Systems, Comparison and Optimization,” Design and Engineering Department, Stellar Group, Jacksonville, Proceeding of ASME International Joint Power Generation Conference, Miami Beach, Florida.
6.
Rice
I. G
,
1995
, “
Steam-Injected Gas Turbine Analysis: Steam Rates
ASME J. Eng. For Gas Turbine and Power
, Vol.
117
, pp.
347
353
.
7.
Larson
E. D.
and
Williams
R. H.
,
1987
,
Steam-Injected Gas Turbines, ASME
J. Eng. For Gas Turbines and Power
, Vol.
109
, p.
55
63
.
8.
De Paepe
M.
and
Dick
E
,
1997
,
Steam Injected Gas Turbines: Cycle Analysis and Feasibility of Water Recuperation
,
European Journal of Mechanical and Environmental Engineering
, Vol.
42
, No.
2
, pp.
67
77
.
9.
Kim T.S., Song C.H., Ro S.T., Kauh S.K., 1999, “Influence of Ambient Condition on Thermodynamic Performance of The Humid Air Turbine Cycle,” Department of Mechanical Engineering, Seel National University, 151–742 South Korea.
10.
Caˇrdu M., Baica M., 2001, “Gas Turbine Installation with Total Water Injection in The Combustion Chamber,” Energy Conversion and Management 2395–2404.
11.
Ghazikhani
M.
,
Manshoori
N.
,
Tafazoli
D
,
2003
, “
Investigation of Ambient Temperature on GE-F5 Gas Turbine Performance
,”
Iranian Journal of Energy
, Vol.
7
pp.
7
15
.
12.
Ghazikhani M., 1993, “Spark ignition Engine Warm-Up and Emissions: Effect of Inlet Air Preheat and Steam Injection,” Dept. of Fuel and Energy, The University of Leeds, Ph.D. Thesis.
13.
Ghazikhani M., Manshoori N., Tafazoli D., 2002, “Investigation of Steam Injection in GE-F5 Gas Turbine,” B.S. Thesis, Dept. of Mechanical Engineering, Ferdowsi University of Mashad, Mashad, IRAN.
14.
Bassily A.M, 2001, “Effects of Evaporative Inlet and after Cooling on the Recuperated Gas Turbine Cycle,” Nuclear Engineering Laboratory, USA.
This content is only available via PDF.
You do not currently have access to this content.