This paper discusses various issues that should be considered when designing the steam system for a typical three pressure reheat cycle, which is used at many of today’s combined cycled plants. A cascade bypass arrangement in the steam system is commonly used to ensure steam flow is available to the reheat section of the HRSG during startup. For the purposes of this paper, a cascade bypass system will be defined as high pressure steam being bypassed to the cold reheat steam and hot reheat steam being bypassed to the condenser. This arrangement can lead to conflicts between plant operation needs and the steam turbine desire to reduce the HP turbine backpressure as much as possible during startup. Plant operation needs that may dictate keeping the reheat system pressure high include export steam minimum pressure guarantees to customers, cycling operation which forces the plant to restart when equipment is still hot, and hot reheat steam bypass or condenser limitations. The HP turbine and cold reheat steam piping can have temperature limitations which may necessitate keeping the HP turbine exhaust pressure as low as possible during startup.
Skip Nav Destination
2002 International Joint Power Generation Conference
June 24–26, 2002
Scottsdale, Arizona, USA
Conference Sponsors:
- Power Division
ISBN:
0-7918-3617-7
PROCEEDINGS PAPER
Steam System Design Considerations for Three Pressure Reheat Cycles With Cascade Bypass System
Brandon Greer,
Brandon Greer
Bechtel Power Corporation, Frederick, MD
Search for other works by this author on:
Kurt Schnaithmann,
Kurt Schnaithmann
Alstom Power Generation, Mannheim, Germany
Search for other works by this author on:
Stefan Klatt
Stefan Klatt
Alstom Power Generation, Mannheim, Germany
Search for other works by this author on:
Brandon Greer
Bechtel Power Corporation, Frederick, MD
Kurt Schnaithmann
Alstom Power Generation, Mannheim, Germany
Stefan Klatt
Alstom Power Generation, Mannheim, Germany
Paper No:
IJPGC2002-26116, pp. 555-562; 8 pages
Published Online:
February 24, 2009
Citation
Greer, B, Schnaithmann, K, & Klatt, S. "Steam System Design Considerations for Three Pressure Reheat Cycles With Cascade Bypass System." Proceedings of the 2002 International Joint Power Generation Conference. 2002 International Joint Power Generation Conference. Scottsdale, Arizona, USA. June 24–26, 2002. pp. 555-562. ASME. https://doi.org/10.1115/IJPGC2002-26116
Download citation file:
13
Views
Related Proceedings Papers
Related Articles
Reheating in Steam Turbines
Trans. ASME (August,1949)
A Computational Model of a Combined Cycle Power Generation Unit
J. Energy Resour. Technol (September,2004)
Last Stage Performance Considerations in Low-Pressure Turbines of Power Plants: A Case Study
J. Eng. Gas Turbines Power (March,2008)
Related Chapters
Lay-Up and Start-Up Practices
Consensus on Operating Practices for Control of Water and Steam Chemistry in Combined Cycle and Cogeneration
Combined Cycle Power Plant
Energy and Power Generation Handbook: Established and Emerging Technologies
Performance Testing of Combined Cycle Power Plant
Handbook for Cogeneration and Combined Cycle Power Plants, Second Edition