A project with the acronym IRBIS (Ignalina Risk Based Inspection pilot Study) has been performed with the objective to perform a quantitative risk analysis of a total of 1240 stainless steel welds in Ignalina Nuclear Power Plant, unit 2 (INPP-2). The damage mechanism is IGSCC and the failure probabilities are quantified by using probabilistic fracture mechanics. The conditional core damage probabilities are taken from the plant PSA.
Volume Subject Area:
Safety, Reliability and Plant Evaluations
This content is only available via PDF.
Copyright © 2002
by ASME