Five WWER-440 reactors are being dismantled on the Greifswald Nuclear Power Plant (KGR) site. The strategy for the dismantling of the reactor units 1 to 4 (operation time 12–17 years) was to cut and pack the components remotely. For this purpose dry and wet cutting areas were installed. The remote cutting and packing of the reactor pressure vessel and its internals was successfully tested with non-activated original reactor components of units 7 and 8 from October 1999 until July 2003. From August 2004 until July 2007 the internals from reactor units 1 and 2 were cut, packed and transported to the on-site Interim Store North (ISN). For the reactor 5 it was planned to transport the RPV in one piece and the reactor internals in shielding and transport containers to the interim store for decay storage. In December 2003 the RPV of unit 5 was lifted and transported to the interim store. From April 2006 up to July 2006 the reactor internals of unit 5 were packed and transported to the interim store. After the evaluation of the experience made during the transport and the radiological measurements and samplings taken from the RPV unit 1, the strategy for the dismantling of the reactors was changed. The reactor pressure vessels of the units 1 to 4 and the reactor internals of the units 3 and 4 should be removed as complete parts and stored as shielded large components in the ISN. In summer 2005 EWN applied for the new strategy at the responsible licensing authority and in August 2007 this license was granted. In November 2007 the reactor pressure vessels of the units 1 and 2 were transported into the ISN. The transport of the reactor pressure vessels and the internals from units 3 and 4 is planned in the period from March till September 2009. These transports of the reactor pressure vessels and internals show that the dismantling of the reactors with dismantling and interim storage of large components could not only be an alternative for cutting but could also be favored from the economical and radiological point of view.
Skip Nav Destination
ASME 2009 12th International Conference on Environmental Remediation and Radioactive Waste Management
October 11–15, 2009
Liverpool, UK
Conference Sponsors:
- Nuclear Engineering Division and Environmental Engineering Division
ISBN:
978-0-7918-4408-3
PROCEEDINGS PAPER
Transport of the Reactor Pressure Vessels in the Greifswald Nuclear Power Plant
Ralf Borchardt
Ralf Borchardt
Energiewerke Nord GmbH, Lubmin, Germany
Search for other works by this author on:
Ralf Borchardt
Energiewerke Nord GmbH, Lubmin, Germany
Paper No:
ICEM2009-16012, pp. 63-68; 6 pages
Published Online:
December 12, 2010
Citation
Borchardt, R. "Transport of the Reactor Pressure Vessels in the Greifswald Nuclear Power Plant." Proceedings of the ASME 2009 12th International Conference on Environmental Remediation and Radioactive Waste Management. ASME 2009 12th International Conference on Environmental Remediation and Radioactive Waste Management, Volume 2. Liverpool, UK. October 11–15, 2009. pp. 63-68. ASME. https://doi.org/10.1115/ICEM2009-16012
Download citation file:
15
Views
Related Proceedings Papers
Related Articles
The Fabulous Nuclear Odyssey of Belgium
J. Pressure Vessel Technol (June,2009)
Three-Dimensional Profilometry Utilization on VVER Type Reactors
ASME J of Nuclear Rad Sci (April,2021)
Investigation of the Beltline Welding Seam and Base Metal of the Greifswald WWER-440 Unit 1 Reactor Pressure Vessel
J. Eng. Gas Turbines Power (May,2011)
Related Chapters
Subsection NCA—General Requirements for Division 1 and Division 2
Companion Guide to the ASME Boiler & Pressure Vessel Code, Volume 1, Second Edition
Subsection NCA—General Requirements for Division 1 and Division 2
Companion Guide to the ASME Boiler and Pressure Vessel Code, Volume 1, Third Edition
Lessons Learned: NRC Experience
Continuing and Changing Priorities of the ASME Boiler & Pressure Vessel Codes and Standards