Abstract
SCK•CEN is dismantling its small BR3 PWR reactor. For the management of the contaminated loops, we decided first to decrease the dose rate by a chemical decontamination of the circuits. A complete dismantling of the loops and of the equipment’s follows this. After a careful sorting of the pieces, we select the optimised management route, which will lead to a minimum of radioactive waste disposed. This paper gives the results of the management of the pieces arising from the dismantling of the most contaminated loops of the plant. We show that it is possible to recycle most of the metallic materials either in the nuclear world or in the industrial world by reaching the respective recycling or clearance criteria.
Volume Subject Area:
D&D of Nuclear Reactors
This content is only available via PDF.
Copyright © 2001 by ASME
You do not currently have access to this content.