This report highlights many difficulties, covering a period of two years, of gas compressor commissioning in the Brent Field. It is intended to give an insight of the problems encountered, with the objective to, wherever possible, avoid repetition. It is in most cases the DESIGN STAGE, where the lessons learned should be implemented, because it is very often too difficult and sometimes impossible to make improvements in compressor modules of offshore platforms.